|  
2024 Eastman Road Widening and Rehabilitation Project

Project Limits:

Monroe Rd. to south of Mier Rd.

Project Length:

2.00 Miles

Construction timeline:

March 2024 thru October 2024

Tree and Brush Clearing:

March 18, 2024 thru April 14, 2024

Roadway Construction:

Start Date: June 3, 2024

Paving Complete by: August 30, 2024

All Construction Complete by: October 11, 2024

Project Bid Amount:

$1,868,853.00

Prime Contractor:

Malley Construction, Inc.

Midland County Road Commission will be widening and rehabilitating Eastman Road in 2024.

 

Key improvements provided by this project include:

  • Paved shoulder widening to provide for non-motorized traffic
  • Road and storm drainage improvements
  • Asphalt pavement overlay

** ACCESS TO BUSINESSES WILL BE MAINTAINED **

 

 For everyone’s safety please follow these traffic tips:

  • During construction hours traffic will be reduced to 1-lane with flagged traffic control alternating cars traveling each direction.
  • When exiting a business, be patient and wait for a vehicle to pass and go with the flow of traffic.
  • Keep speeds less than 45 mph.
  • Try to stay grouped with traffic ahead of you.
Location Map